| Assignment 2 | Assignment 3 | Assignment 4 | Assignment 5 | Assignment 6 | |
Assignment 4The Scheduling Formula: Duration, Units, and Work |
|||||
Project calculates work using what is sometimes called the scheduling formula:
Let’s look at a specific example. The duration of task 2 is five days. For our TV commercial project, five days equals 40 hours. When you assigned Garrett R. Vargas to task 2, Project applied 100 percent of Garrett’s working time to this task. The scheduling formula for task 2 looks like this:
In other words, with Garrett assigned to task 2 at 100 percent units, the task
should Here’s a more complex example. You assigned two resources, each
at 100 percent
The 32 hours of work is the sum of Peter’s 16 hours of work plus Scott’s
16 hours of Assigning Additional Resources to a TaskNow you will assign additional resources to some of the pre-production tasks to see the effect on the overall duration of the tasks. By default, Project uses a scheduling method called effort-driven scheduling. This means that the task's initial work value remains constant, regardless of the number of additional resources you assign. The most visible effect of effort-driven scheduling is that as you assign additional resources to a task, that task's duration decreases. Project applies effort-driven scheduling only when you assign resources to or remove resources from tasks. As you saw previously, you define the amount of work a task represents when you initially assign a resource or resources to it. With effort-driven scheduling turned on, if you later add resources to that task, the amount of work for the task does not change but the task's duration decreases. Or you might initially assign more than one resource to a task and later remove one of those resources from the task. With effort-driven scheduling on, the amount of work for the task stays constant. The duration, or time it takes the remaining resource to complete that task, increases.
In this exercise, you assign additional resources to tasks and see how this affects task durations. 1. In the Gantt Chart view, click the name of task 2, Develop script. Currently, Garrett R. Vargas is assigned to this task. A quick check of the scheduling formula looks like this: 40 hours (the same as 5 days) task duration × 100% of Garrett's assignment units = 40 hours work. If you want, you can scroll the Assign Resources pane down to see these values. Next you will assign a second resource to the task. 2. In the Resource Name column in the Assign Resources dialog box, click Scott Cooper, and click the Assign button. Scott Cooper is assigned to task 2. Your screen should look similar to the following illustration:
As you can see in the Gantt Chart view, Project reduced the duration of task 2 from 5 days to 2.5 days. The total work required is still 40 hours, as it was when only Garrett was assigned to the task, but now the work is distributed evenly between Garrett and Scott. This shows how effort-driven scheduling works. If, after an initial assignment, you add resources to a task, the total work remains constant but is distributed among the assigned resources. Further, the task's duration decreases accordingly. The scheduling formula now looks like this: 20 hours (the same as 2.5 days) task duration × 200% assignment units = 40 hours work The 200 percent assignment units is the sum of Garrett's 100 percent plus Scott's 100 percent, and the 40 work hours is the sum of Garrett's 20 hours plus Scott's 20 hours. The other important effect of reducing the duration of task 2 is that the start dates of all successor tasks have changed as well. In Assignment 1, you created finish-to-start task relationships for these tasks. In this example, you see the benefit of creating task relationships rather than entering fixed start and finish dates. Project adjusts the start dates of successor tasks that do not have a constraint, such as a fixed start date or finish date. Next you assign multiple resources to other tasks, using a Smart Tag to control how Project schedules the work on the tasks. 3. In the Gantt Chart view, click the name of task 4, Pick locations. Currently, only Scott Cooper is assigned to this two-day task. You'd like to assign an additional resource and reduce the task's duration to one day. 4. In the Resource Name column of the Assign Resources dialog box, click Patti Mintz, and then click the Assign button. Patti Mintz is also assigned to task 4.
5. Click the Smart Tag Actions button. Your screen should look like the following:
These options let you choose the scheduling result you want, should it differ from the effort-driven scheduling result. You can adjust the task's duration, the resource's work, or the assignment units. For this task, you want the additional resource assignment to reduce the task's duration. Because this is the default setting in the Smart Tag Actions list, you don't need to make any changes. 6. Click the Smart Tag Actions button again to close the list.
7. In the Gantt Chart view, click the name of task 5, Hold auditions. 8. In the Resource Name column of the Assign Resources dialog box, click Jonathan Mollerup, hold down the Ctrl key, click Patti Mintz, and then click the Assign button. Project assigns Jonathan and Patti to the task.
However, this time you do not want the additional resouce assignments to change the task's duration. You have had a flood of people wanting to audition and Jonathan and Patti will work on the extra auditions.
9. Click the Smart Tag Actions button. 10. In the Smart Tag Actions list, select the option Increase total work because the task requires more person-hours. Keep duration constant. Project changes the task's duration back to two days and adjusts the start dates of all successor tasks. The additional resources get the same work values that the initially assigned resources had, so the total work on the task increases. Your screen should look similar to the following illustration:
Project Management Focus: When Should Effort-Driven Scheduling Apply? You should think through the extent to which effort-driven scheduling should apply to the tasks in your projects. For example, if one resource should take 10 hours to complete a task, could 10 resources complete the task in one hour? How about 20 resources in 30 minutes? Probably not; the resources would likely get in each other's way and require additional coordination to complete the task. If the task is very complicated, it might require significant ramp-up time before a resource could contribute fully. Overall productivity might even decrease if you assign more resources to the task. No single rule exists about when you should apply effort-driven scheduling and when you should not. As the project manager, you should analyze the nature of the work required for each task in your project and use your best judgment. 81 |
|||||
Assigning Material Resources to Tasks Previously, you created the material resource named Video Tape. In our TV commercial project, we are interested in tracking the use of video cassettes and their cost. When assigning a material resource, you can handle consumptions and cost in one of two ways:
In this exercise, you assign the material resource Video Tape to a task and enter a fixed-unit quantity of consumption. You will also work with the more complete version of the Assign Resources dialog box. 1. In the Assign Resources dialog box, click the Close button. 2. Click the Show/Hide Project Guide button on the Project Guide toolbar. The Project Guide closes. 3. On the Standard toolbar, click the Assign Resources button
4. In the Task Name column, click the name of task 4, Pick locations. You plan to use up to four tapes while picking locations. 5. In the Assign Resources dialog box, select the Units field for the Video Tape resource. 6. Type 4, and then click the Assign button. Project assigns the video tape to the task. Your screen should look like the following illustration: 82
Key Points
|
|||||
|
Print your Gantt view as well as the Task Usage view (View>Task Usage) which should look similar to the illustrations below
|
|||||