Assignment 1Plan a Commercial 1 |
|||||
Open Microsoft Project 2007. If it is not already showing, select View>Turn on Project Guide. Make sure you are in the Ghantt Chart view (View> Gant)
If the task pane is not already displayed, clickTasks on the Project Guide Toolbar |
|||||
| In the tasks pane select List the Tasks | |||||
List the following tasks in the Task name panel
Complete the durations as shown
|
|
||||
An important event such as the end of a phase can be indicated as a milestone
|
|||||
Organize tasks into phases
|
|
||||
|
You can also click the Link Tasks button on the standard toolbar or select Edit>Link Tasks to create this finish-to-start dependancy. You can unlink tasks by selecting the tasks and click Unlink Tasks on the Standard toolbar or select Edit>Unlink Tasks Click here to see a detailed explanation of link types
The results are below.
Now select the names of tasks 3 through 6 and link them with a Finish-toStart Link
|
|
||||
Next you will link two tasks in a different way. We are going to make task 8 a predecessor of task 9
|
|
||||
Select the names of tasks 8, 9 and 10. Link them with a Finish-to-Start Link
Finaly, select the name of task 1, and while holding
down the CTRL key, select the name
of task 7. In the Schedule
Tasks pane, make this a Finish-to-start link. This is called a non-adjacent link. |
|||||